Deepwater pipeline procedure development for COOEC. A full set of general deep water, 1000m to 3000m, installation procedures were developed.
Design of pig receivers, work platforms, and handling systems. Fabrication and delivery of piping spools…
Pipelay operation management and training. GMC provided offshore consultants on the Lan Jiang Laybarge, including…
Perform offshore pipeline lateral stability analysis and create pipeline alignment sheet and trench profile. Work…
Installation analysis, installation aid design, and procedure development for one jacket, one topside, two 8”…
Installation analysis of 4km of 10” flexible pipe offshore UAE. The line was initiated via…
Structural analysis of existing platform. Design of all pipe handling equipment, modifications to the platform…